can anyone solve this plzz ( IQ test )

Messages
663
Reaction score
282
Points
73
5 men are hired to complete a certain job , if an additional man is hired , the job can be completed 8 days earlier . given that the number of days required to complete the job is inversely proportional to the number of men hired , find the number of additional men hired to complete the job 28 days earlier ????
 
Messages
1,477
Reaction score
1,893
Points
173
5 men are hired to complete a certain job , if an additional man is hired , the job can be completed 8 days earlier . given that the number of days required to complete the job is inversely proportional to the number of men hired , find the number of additional men hired to complete the job 28 days earlier ????



5 men do it in x days
6 men do it in (x - 8) days

using inverse proportion ,

5x = 6(x - 8)
5x = 6x - 48
x = 48

--------------------------------------------------------
5 men do it in x days
(5 + m) men do it in (x - 28) days

using inverse proportion,

5x = (5 + m) (x - 28)

Substitute x = 48

240 = (5 + m) (20)
12 = (5 + m)
m = 7


7 additional men needed. (7 + 5 = 13 men in total)
 