• We need your support!

    We are currently struggling to cover the operational costs of Xtremepapers, as a result we might have to shut this website down. Please donate if we have helped you and help make a difference in other students' lives!
    Click here to Donate Now (View Announcement)

Economics, Accounting & Business: Post your doubts here!

Messages
323
Reaction score
112
Points
53
Messages
402
Reaction score
262
Points
73

Direct labour hour rate is 5.4 per hour and each unit takes 4 hours. which means OAR is 5.4 multiplied by 4. (21.6)

And as the question states that it is under absorbed which means overhead absorbed is less than incurred cost, we deduct 32400 from 518400. (486000)

Then it is divided by the oar amount 21.6 to give the actual units produced 22500 units.
 
Messages
323
Reaction score
112
Points
53
Direct labour hour rate is 5.4 per hour and each unit takes 4 hours. which means OAR is 5.4 multiplied by 4. (21.6)

And as the question states that it is under absorbed which means overhead absorbed is less than incurred cost, we deduct 32400 from 518400. (486000)

Then it is divided by the oar amount 21.6 to give the actual units produced 22500 units.
thanks alot
 
Top